Crossref DOIMemberCiteFactoropen accessissn
SJIF Impact Factor 8.659 | ISSN: 2582-3930
IJSREM Logo

International Journal of Scientific Research in Engineering and Management

(Gateway to Global Scholars - An International, Scholarly, Multi-Disciplinary, Open Access Journal)

Peer-Reviewed Journal Designed to Meet UGC's Quality Parameters

HomeCurrent IssuePast IssuesPay OnlineConferencesEditorial BoardAbout UsContact Us
IJSREM

Loading article...

Follow Us

  • Google Scholar
  • ResearchGate
  • Academia.edu
  • Mendeley
  • LinkedIn
  • Facebook
  • Instagram

Journal Policies

  • Peer Review Policy
  • Publication Ethics
  • Copyright Infringement
  • Refund & Cancellation Policy
  • Terms and Conditions
  • Privacy Policy

Journal Identifiers & Licenses

  • ISSN Verified: 2582-3930ISSN Verified: 2582-3930
  • Crossref DOI: 10.55041Crossref DOI: 10.55041
  • SJIF Ranking: 08.659SJIF Ranking: 08.659
  • Licensed under CC BY 4.0Licensed under CC BY 4.0
  • ISO Certification: 9001:2015ISO Certification: 9001:2015
  • Indexed & Cited In: Google ScholarIndexed & Cited In: Google Scholar

Contact Us

International Journal of Scientific Research in Engineering and Management (IJSREM)

#62/1, New No 7, 1st Cross, 2nd Main, Ganganagar, R T Nagar, Bangalore North, Bangalore, Karnataka, India – 560032
[email protected]+91 93911 67991
logos
logos
Working Hours

Mon – Sat: 9:00 AM – 6:00 PM

Sunday: 10:00 AM – 4:00 PM

+91 93911 67991

© 2026 IJSREM – International Journal of Scientific Research in Engineering and Management. This is an open-access journal. Articles are published under the Creative Commons Attribution (CC BY 4.0) License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

DisclaimerPrivacy PolicyTerms and Conditions
ArticlePeer ReviewedOpen AccessPlagiarism Passed
Paper ID:IJSREM47227

Factors Affecting Time and Cost Overrun – Indian Scenario.

Stream/Area:

-

Subject:

-

Paper ID:

IJSREM47227

Volume:

9 |

5 |

May 2025

Pages:

Publication Frequency:

Monthly (12 issues per year)

DOI
Digital Object Identifier
10.55041/IJSREM47227

License:International Journal of Scientific Research in Engineering and Management follows the Creative Commons Attribution 4.0 (CC BY 4.0) License, allowing free use and distribution with proper attribution.

Share this article:

Authors

MSSM1

Mr. Sanved Sharad More 1

DDD2

Dr. D.B. Desai 2

MAPC

Mrs. A. P. Chougule3

Author Services & Downloads

Full Articles

Abstract

In the Indian construction industry, time and cost overruns are an ongoing issue, especially for major road infrastructure projects. Using information from primary data gathered through structured surveys as well as literature, this study examines the main causes of these overruns. Finding the most significant causes, evaluating their relative effects, and making useful suggestions for minimizing them were the goals of the study. To determine the fundamental factors causing delays in projects and cost increases, a thorough literature review was carried out. A questionnaire survey was created and distributed to industry professionals working on road infrastructure projects in light of these findings. In order to rank the degree to which each aspect affected time and cost performance, the responses that were gathered were examined. The findings revealed that the main causes of project overruns were changes to the scope during execution, construction mistakes, problems with bill settlement, construction accidents, and rising fuel and material costs. In order to reduce overruns, the study’s conclusion highlights the necessity of better planning, effective stakeholder communication and contractual risk allocation. Policymakers, contractors and project managers looking to improve the effectiveness and sustainability of infrastructure development in India will find the findings to be a useful resource.

KEYWORDS

Time overrun Cost overrun Indian construction Industry Likert’s scale.

Cite This Article

Mr. Sanved Sharad More 1, Dr. D.B. Desai 2, Mrs. A. P. Chougule3, "Factors Affecting Time and Cost Overrun – Indian Scenario.," International Journal of Scientific Research in Engineering and Management, vol. 9, no. 5, May 2025. https://doi.org/10.55041/IJSREM47227

Full Article/Conclusion

References

Editorial & Review Transparency

Publication Date

9/4/2025

Peer Review Type

Double-Blind Peer Review

Review Rounds: 2

Documents

Review Report (Confidential)
Copyright Form (Office)

Article Metrics & Impact

Article Views

0

Total views since publication

PDF Downloads

4

Total downloads since publication

Geographic Reach

5

Indexing, Archiving & Preservation

Google Scholar
Academia
ResearchGate
Crossref
SSRN
Semantic Scholar
Thomson Reuters
WorldCat
Mendeley
OpenAlex
EBSCO
Zenodo

Digital Preservation: This article is permanently archived on Zenodo and complies with all data preservation standards across major indexing platforms.

Ethics, Compliance & Transparency

Plagiarism Screening

This manuscript has been checked for plagiarism using TurnitinPlagiarismChecker software.

Conflict of Interest

The authors declare no conflict of interest related to this research work.

Funding Information

No funding information available for this research.

Similar & Recommended Articles

Similar Articles by Topic

Related research in the same subject area

Loading similar articles...