Crossref DOIMemberCiteFactoropen accessissn
SJIF Impact Factor 8.659 | ISSN: 2582-3930
IJSREM Logo

International Journal of Scientific Research in Engineering and Management

(Gateway to Global Scholars - An International, Scholarly, Multi-Disciplinary, Open Access Journal)

Peer-Reviewed Journal Designed to Meet UGC's Quality Parameters

HomeCurrent IssuePast IssuesPay OnlineConferencesEditorial BoardAbout UsContact Us
IJSREM

Loading article...

Follow Us

  • Google Scholar
  • ResearchGate
  • Academia.edu
  • Mendeley
  • LinkedIn
  • Facebook
  • Instagram

Journal Policies

  • Peer Review Policy
  • Publication Ethics
  • Copyright Infringement
  • Refund & Cancellation Policy
  • Terms and Conditions
  • Privacy Policy

Journal Identifiers & Licenses

  • ISSN Verified: 2582-3930ISSN Verified: 2582-3930
  • Crossref DOI: 10.55041Crossref DOI: 10.55041
  • SJIF Ranking: 08.659SJIF Ranking: 08.659
  • Licensed under CC BY 4.0Licensed under CC BY 4.0
  • ISO Certification: 9001:2015ISO Certification: 9001:2015
  • Indexed & Cited In: Google ScholarIndexed & Cited In: Google Scholar

Contact Us

International Journal of Scientific Research in Engineering and Management (IJSREM)

#62/1, New No 7, 1st Cross, 2nd Main, Ganganagar, R T Nagar, Bangalore North, Bangalore, Karnataka, India – 560032
[email protected]+91 93911 67991
logos
logos
Working Hours

Mon – Sat: 9:00 AM – 6:00 PM

Sunday: 10:00 AM – 4:00 PM

+91 93911 67991

© 2026 IJSREM – International Journal of Scientific Research in Engineering and Management. This is an open-access journal. Articles are published under the Creative Commons Attribution (CC BY 4.0) License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

DisclaimerPrivacy PolicyTerms and Conditions
ArticlePeer ReviewedOpen AccessPlagiarism Passed
Paper ID:10.55041/IJSREM18358

Identify Causes of Delay and Cost overrun in Residential Construction Projects at Surat Region in India: A Review

Stream/Area:

-

Subject:

-

Paper ID:

10.55041/IJSREM18358

Volume:

7 |

3 |

Mar 2023

Pages:

Publication Frequency:

Monthly (12 issues per year)

DOI
Digital Object Identifier
Not assigned

License:International Journal of Scientific Research in Engineering and Management follows the Creative Commons Attribution 4.0 (CC BY 4.0) License, allowing free use and distribution with proper attribution.

Share this article:

Authors

KRP

Kirtankumar R. Panchal

DJP

Dr. J.R. Pitroda

PANB

Prof. A. N. Bhavsar

PJK

P. J. Kansara

Author Services & Downloads

Full Articles

Abstract

A construction project is deemed successful if it is finished within the timeframe provided. A variety of variables lead to project major failure. Construction delays and cost overruns are two of them. Project delays impede growth in all other connected disciplines. A project delays study was conducted to examine the delay causes, the impact of delays, and techniques for decreasing construction delays. Poor performance measure is a typical concern in building projects, with few projects finishing on time and within budget. According to previous studies (publications), around 90% of construction projects have delays and cost overruns ranging from 5% to 200%. The research includes a literature review as well as a questionnaire survey. A detailed questionnaire survey was used to collect data for this investigation. The building of the urban development project is significantly more challenging due to the large number of players involved. These parties include the client, contractors, architect, suppliers, consultants, and labours. It is essential to figure out whether delay is crucial or not, as identifying the critical delays aids in the implementation of relevant actions at the proper time. The purpose of this research is to assess the various forms of delays as well as the reasons of those delays that are hurting projects in India’s Surat area. 8 main groups were responsible for construction delays. The weights of the delay factors and groups were computed and evaluated. An examination of the literature revealed 45 variables that influence delays. The questionnaire was distributed to construction projects.

KEYWORDS

Construction Project Delay Cost overrun Time Process Factors Management client contractor designer suppliers consultant and labours India.

Cite This Article

Kirtankumar R. Panchal, Dr. J.R. Pitroda, Prof. A. N. Bhavsar, P. J. Kansara, "Identify Causes of Delay and Cost overrun in Residential Construction Projects at Surat Region in India: A Review," International Journal of Scientific Research in Engineering and Management, vol. 7, no. 3, Mar 2023. https://doi.org/10.55041/IJSREM18358

Full Article/Conclusion

References

Editorial & Review Transparency

Publication Date

3/27/2023

Peer Review Type

Double-Blind Peer Review

Review Rounds: 2

Documents

Review Report (Confidential)
Copyright Form (Office)

Article Metrics & Impact

Article Views

1

Total views since publication

PDF Downloads

2

Total downloads since publication

Geographic Reach

5

Indexing, Archiving & Preservation

Google Scholar
Academia
ResearchGate
Crossref
SSRN
Semantic Scholar
Thomson Reuters
WorldCat
Mendeley
OpenAlex
EBSCO
Zenodo

Digital Preservation: This article is permanently archived on Zenodo and complies with all data preservation standards across major indexing platforms.

Ethics, Compliance & Transparency

Plagiarism Screening

This manuscript has been checked for plagiarism using TurnitinPlagiarismChecker software.

Conflict of Interest

The authors declare no conflict of interest related to this research work.

Funding Information

No funding information available for this research.

Similar & Recommended Articles

Similar Articles by Topic

Related research in the same subject area

Loading similar articles...