Crossref DOIMemberCiteFactoropen accessissn
SJIF Impact Factor 8.659 | ISSN: 2582-3930
IJSREM Logo

International Journal of Scientific Research in Engineering and Management

(Gateway to Global Scholars - An International, Scholarly, Multi-Disciplinary, Open Access Journal)

Peer-Reviewed Journal Designed to Meet UGC's Quality Parameters

HomeCurrent IssuePast IssuesPay OnlineConferencesEditorial BoardAbout UsContact Us
IJSREM

Loading article...

Follow Us

  • Google Scholar
  • ResearchGate
  • Academia.edu
  • Mendeley
  • LinkedIn
  • Facebook
  • Instagram

Journal Policies

  • Peer Review Policy
  • Publication Ethics
  • Copyright Infringement
  • Refund & Cancellation Policy
  • Terms and Conditions
  • Privacy Policy

Journal Identifiers & Licenses

  • ISSN Verified: 2582-3930ISSN Verified: 2582-3930
  • Crossref DOI: 10.55041Crossref DOI: 10.55041
  • SJIF Ranking: 08.659SJIF Ranking: 08.659
  • Licensed under CC BY 4.0Licensed under CC BY 4.0
  • ISO Certification: 9001:2015ISO Certification: 9001:2015
  • Indexed & Cited In: Google ScholarIndexed & Cited In: Google Scholar

Contact Us

International Journal of Scientific Research in Engineering and Management (IJSREM)

#62/1, New No 7, 1st Cross, 2nd Main, Ganganagar, R T Nagar, Bangalore North, Bangalore, Karnataka, India – 560032
[email protected]+91 93911 67991
logos
logos
Working Hours

Mon – Sat: 9:00 AM – 6:00 PM

Sunday: 10:00 AM – 4:00 PM

+91 93911 67991

© 2026 IJSREM – International Journal of Scientific Research in Engineering and Management. This is an open-access journal. Articles are published under the Creative Commons Attribution (CC BY 4.0) License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

DisclaimerPrivacy PolicyTerms and Conditions
ArticlePeer ReviewedOpen AccessPlagiarism Passed
Paper ID:IJSREM66692

Implementation of Lean Construction Techniques Using Microsoft Project (MSP) for Time and Cost Optimization in Residential Building Projects: A Review

Stream/Area:

-

Subject:

-

Paper ID:

IJSREM66692

Volume:

10 |

8 |

Aug 2026

Pages:

1-8

Publication Frequency:

Monthly (12 issues per year)

DOI
Digital Object Identifier
Not assigned

License:International Journal of Scientific Research in Engineering and Management follows the Creative Commons Attribution 4.0 (CC BY 4.0) License, allowing free use and distribution with proper attribution.

Share this article:

Authors

AVP

Avadhoot V. Patil

Civil Engineering

JJMCOE, Jaysinghpur

Download Author Certificate

Mentors

PASS

Prof. Amitkumar S. Sajane

Assistant Professor, Civil Engineering,

JJMCOE, Jaysinghpur, Maharastra, India

Download Mentor Certificate

Author Services & Downloads

Full ArticlesAcceptance Certificate

Abstract

The construction industry continuously faces challenges related to project delays, material wastage, inventory management, labor inefficiencies, and cost overruns. Lean Construction (LC) and Just-in-Time (JIT) methodologies have emerged as effective approaches to enhance project performance by minimizing non-value-adding activities and improving workflow efficiency. This paper presents a comprehensive review of recent literature on Lean Construction and JIT implementation in construction projects, with particular emphasis on prefabrication, modular construction, Building Information Modeling (BIM), Artificial Intelligence (AI), automation, and digital technologies. A systematic review of recent studies published between 2021 and 2026 was conducted to identify current research trends, implementation strategies, benefits, challenges, and research gaps. The review indicates that integrating Lean principles with JIT delivery, prefabrication, AI-enabled planning, computer vision, digital twins, and Industry 4.0 technologies significantly improves productivity, reduces material waste, shortens project duration, enhances resource utilization, and increases overall project quality. Despite these advancements, several challenges remain, including fragmented supply chains, inadequate integration between JIT and prefabricated construction, limited real-time decision-making capabilities, resistance to organizational change, and the absence of standardized implementation frameworks. The study identifies these research gaps and highlights the need for integrated Lean–JIT frameworks supported by digital technologies for sustainable and efficient construction management. The findings provide valuable insights for researchers, industry practitioners, and policymakers seeking to improve construction project performance through lean-based management strategies and establish directions for future research in smart and sustainable construction.

KEYWORDS

Lean Construction Just-in-Time (JIT) Prefabrication Modular Construction Building Information Modeling (BIM) Industry 4.0 Artificial Intelligence Construction Management Waste Reduction Sustainable Construction.

Cite This Article

Avadhoot V. Patil, Prof. Amitkumar S. Sajane, "Implementation of Lean Construction Techniques Using Microsoft Project (MSP) for Time and Cost Optimization in Residential Building Projects: A Review," International Journal of Scientific Research in Engineering and Management, vol. 10, no. 8, pp. 1-8, Aug 2026.

Full Article/Conclusion

This study investigated the application of Just-in-Time (JIT) material management integrated with prefabricated construction as an effective lean construction strategy for improving project performance. A comprehensive review of the existing literature revealed that lean construction principles, Building Information Modeling (BIM), Internet of Things (IoT), Integrated Project Delivery (IPD), and prefabrication have individually contributed to enhancing construction productivity, reducing waste, and improving sustainability. However, limited research has focused on the combined implementation of JIT material management and prefabricated construction, particularly under Indian construction conditions.The critical analysis demonstrated that JIT significantly reduces inventory levels, storage requirements, material handling, and site congestion by ensuring timely delivery of construction components. Prefabrication complements JIT by enabling off-site manufacturing, improving quality control, reducing on-site labor dependency, minimizing material waste, and accelerating project completion. The integration of these approaches supports lean construction objectives by creating a continuous workflow, improving coordination among stakeholders, and enhancing overall project efficiency. The literature further indicated that although modern technologies such as BIM, IoT, cloud computing, and simulation models have strengthened lean construction practices, their practical implementation remains limited in many developing countries. Existing studies primarily emphasize productivity improvement and waste reduction, while comparatively fewer investigations have comprehensively evaluated inventory optimization, logistics performance, cost efficiency, and schedule improvement through JIT-enabled prefabrication. Furthermore, most previous research is based on conceptual frameworks, literature reviews, questionnaire surveys, or geographically limited case studies, indicating the need for more empirical investigations.Based on the findings of this study, it can be concluded that the successful integration of Just-in-Time material management with prefabricated construction has significant potential to improve construction productivity, reduce project duration, lower inventory and storage costs, minimize material waste, optimize resource utilization, and enhance project quality. The combined implementation also contributes to sustainable construction by reducing unnecessary transportation, minimizing environmental impacts, and improving overall project management efficiency. The present study addresses an important research gap by providing a comprehensive analysis of lean construction techniques and highlighting the benefits of integrating JIT with prefabrication. The findings provide useful guidance for construction managers, project planners, contractors, and policymakers seeking to improve project performance through lean practices. Future research should focus on large-scale field implementation across different construction sectors, quantitative performance assessment using real project data, economic analysis of life-cycle benefits, and integration of emerging technologies such as Artificial Intelligence (AI), Digital Twins, BIM 5D, and advanced IoT systems to further strengthen lean construction practices and support the digital transformation of the construction industry.

References

1.    Lakmal, D. (2014). Managing the challenge of generational diversity in the workplace. SSRN, 1-11. 2.    Dixit, S. (2018). Analysing enabling factors affecting on-site productivity in the Indian construction industry. Periodica Polytechnica Architecture, 49(2), 185-193. 3.    Aarseth, W., Ahola, T., Aaltonen, K., Økland, A., & Andersen, B. (2017). Project sustainability strategies: A systematic literature review. International Journal of Project Management, 35(6), 1071-1083. 4.    Koskela, L., Ballard, G., Howell, G., & Tommelein, I. (2002). The foundations of lean construction. In Design and Construction: Building in Value (pp. 211-226). 5.    Sarhan, J., Xia, B., Fawzia, S., Karim, A., & Olanipekun, A. (2018). Barriers to implementing lean construction practices in the Kingdom of Saudi Arabia (KSA) construction industry. Construction Innovation, 18(2), 246-272. 6.    Xu, G., Li, M., Chen, C. H., & Wei, Y. (2018). Cloud asset-enabled integrated IoT platform for lean prefabricated construction. Automation in Construction, 93, 123-134. 7.    Kahvandi, R., Ravasan, Z., Saghatforoush, E., Zare Ravasan, A., & Mansouri, T. (2018). An FCM-based dynamic modeling of integrated project delivery implementation challenges in construction projects. Lean Construction Journal, 87, 63-87. 8.    Banawi, A., & Bilec, M. M. (2014). A framework to improve construction processes: Integrating lean, green, and six sigma. International Journal of Construction Management, 14(1), 45-55. 9.    Bertelsen, S. (2004). Lean construction: Where are we and how to proceed?. Lean Construction Journal, 1(October), 46-69. 10. Li, X., Shen, G. Q., Wu, P., Fan, H., Wu, H., & Teng, Y. (2017). RBL-PHP: Simulation of lean construction and information technologies for prefabrication housing production. Journal of Management in Engineering, 34(2), 04017053.

Editorial & Review Transparency

Publication Date

8/13/2026

Peer Review Type

Double-Blind Peer Review

Review Rounds: 2

Documents

Review Report (Confidential)
Copyright Form (Office)

Article Metrics & Impact

Article Views

0

Total views since publication

PDF Downloads

3

Total downloads since publication

Geographic Reach

5

Indexing, Archiving & Preservation

Google Scholar
Academia
ResearchGate
Crossref
SSRN
Semantic Scholar
Thomson Reuters
WorldCat
Mendeley
OpenAlex
EBSCO
Zenodo

Digital Preservation: This article is permanently archived on Zenodo and complies with all data preservation standards across major indexing platforms.

Ethics, Compliance & Transparency

Plagiarism Screening

This manuscript has been checked for plagiarism using TurnitinPlagiarismChecker software.

Conflict of Interest

The authors declare no conflict of interest related to this research work.

Funding Information

No funding information available for this research.

Similar & Recommended Articles

Similar Articles by Topic

Related research in the same subject area

Loading similar articles...