Crossref DOIMemberCiteFactoropen accessissn
SJIF Impact Factor 8.659 | ISSN: 2582-3930
IJSREM Logo

International Journal of Scientific Research in Engineering and Management

(Gateway to Global Scholars - An International, Scholarly, Multi-Disciplinary, Open Access Journal)

Peer-Reviewed Journal Designed to Meet UGC's Quality Parameters

HomeCurrent IssuePast IssuesPay OnlineConferencesEditorial BoardAbout UsContact Us
IJSREM

Loading article...

Follow Us

  • Google Scholar
  • ResearchGate
  • Academia.edu
  • Mendeley
  • LinkedIn
  • Facebook
  • Instagram

Journal Policies

  • Peer Review Policy
  • Publication Ethics
  • Copyright Infringement
  • Refund & Cancellation Policy
  • Terms and Conditions
  • Privacy Policy

Journal Identifiers & Licenses

  • ISSN Verified: 2582-3930ISSN Verified: 2582-3930
  • Crossref DOI: 10.55041Crossref DOI: 10.55041
  • SJIF Ranking: 08.659SJIF Ranking: 08.659
  • Licensed under CC BY 4.0Licensed under CC BY 4.0
  • ISO Certification: 9001:2015ISO Certification: 9001:2015
  • Indexed & Cited In: Google ScholarIndexed & Cited In: Google Scholar

Contact Us

International Journal of Scientific Research in Engineering and Management (IJSREM)

#62/1, New No 7, 1st Cross, 2nd Main, Ganganagar, R T Nagar, Bangalore North, Bangalore, Karnataka, India – 560032
[email protected]+91 93911 67991
logos
logos
Working Hours

Mon – Sat: 9:00 AM – 6:00 PM

Sunday: 10:00 AM – 4:00 PM

+91 93911 67991

© 2026 IJSREM – International Journal of Scientific Research in Engineering and Management. This is an open-access journal. Articles are published under the Creative Commons Attribution (CC BY 4.0) License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

DisclaimerPrivacy PolicyTerms and Conditions
ArticlePeer ReviewedOpen AccessPlagiarism Passed
Paper ID:10.55041/IJSREM27859

MAXIMIZING REAL-TIME MONITORING FOR EFFECTIVE DELAY ANALYSIS IN BRIDGE CONSTRUCTION PROJECTS WITH EVM SCHEDULING

Stream/Area:

-

Subject:

-

Paper ID:

10.55041/IJSREM27859

Volume:

8 |

1 |

Jan 2024

Pages:

Publication Frequency:

Monthly (12 issues per year)

DOI
Digital Object Identifier
10.55041/IJSREM27859

License:International Journal of Scientific Research in Engineering and Management follows the Creative Commons Attribution 4.0 (CC BY 4.0) License, allowing free use and distribution with proper attribution.

Share this article:

Authors

JK

J. Karthick

MPP

Mr. P.A. Prabakaran

MUSV

Ms. U. Sindhu Vaardini

MAAb

Mr. A. Aswin bharath

Author Services & Downloads

Full Articles

Abstract

A bridge is a civil engineering construction that has been used for generations to cross any obstacle below it. There are many conflicts in bridge construction, and they are getting worse every day. A flyover bridge has been constructed to reduce traffic congestion. Project costs may directly rise if there is a delay in completing the work. The act of analyzing a project’s delay and determining its underlying causes is known as delay analysis. A contractual issue at the Zone 3 junction has caused project delays, which have impacted on the project time limit. Delays caused by factors beyond the parties’ control (Force Majeure) and Delays caused by an unbalanced contract. The EVM technique is used for evaluating Bridge Construction, which allows for project tracking. Construction project performance is investigated to determine the possibility of cost and time overruns, as well as the Estimation at Completion (EAC) and To-Complete Performance Index (TCPI) to evaluate how efficiently the remaining financial resources are used. To conduct analysis on the construction project’s performance and identify critical issues regarding schedule and cost, a delayed construction project was chosen as a case study for this project. Delay Analysis was also conducted to determine the causes behind the project’s variance in duration.

KEYWORDS

Stake holder involvement Contingency plan Procurement scheduling Resource management Contractual consideration.

Cite This Article

J. Karthick, Mr. P.A. Prabakaran, Ms. U. Sindhu Vaardini, Mr. A. Aswin bharath, "MAXIMIZING REAL-TIME MONITORING FOR EFFECTIVE DELAY ANALYSIS IN BRIDGE CONSTRUCTION PROJECTS WITH EVM SCHEDULING," International Journal of Scientific Research in Engineering and Management, vol. 8, no. 1, Jan 2024. https://doi.org/10.55041/IJSREM27859

Full Article/Conclusion

References

Editorial & Review Transparency

Publication Date

12/31/45292

Peer Review Type

Double-Blind Peer Review

Review Rounds: 2

Documents

Review Report (Confidential)
Copyright Form (Office)

Article Metrics & Impact

Article Views

0

Total views since publication

PDF Downloads

28

Total downloads since publication

Geographic Reach

5

Indexing, Archiving & Preservation

Google Scholar
Academia
ResearchGate
Crossref
SSRN
Semantic Scholar
Thomson Reuters
WorldCat
Mendeley
OpenAlex
EBSCO
Zenodo

Digital Preservation: This article is permanently archived on Zenodo and complies with all data preservation standards across major indexing platforms.

Ethics, Compliance & Transparency

Plagiarism Screening

This manuscript has been checked for plagiarism using TurnitinPlagiarismChecker software.

Conflict of Interest

The authors declare no conflict of interest related to this research work.

Funding Information

No funding information available for this research.