Loading article...
Loading article...
Stream/Area:
-
Subject:
-
Paper ID:
IJSREM62816
Volume:
10 |
5 |
May 2026
Pages:
1-8
Publication Frequency:
Monthly (12 issues per year)
License:International Journal of Scientific Research in Engineering and Management follows the Creative Commons Attribution 4.0 (CC BY 4.0) License, allowing free use and distribution with proper attribution.
Civil Engineering
TSSM’s Bhivarabai Sawant College of Engineering and Research, Narhe
Civil Engineering
TSSM’s Bhivarabai Sawant College of Engineering and Research, Narhe
The construction industry continuously faces major challenges related to project delays, labor inefficiency, material wastage, and increasing execution costs. Conventional construction practices often involve non-value-added activities that adversely affect productivity and overall project performance. This study investigates the application of Lean Construction principles through Value Stream Mapping (VSM) as an effective tool for optimizing construction workflow and minimizing unnecessary time and cost expenditures. A detailed case study was conducted on a residential building project located at Green County Phase II, Pune, India. Existing construction activities were analyzed under the Current State Map framework, and improved execution strategies were developed through the Future State Map by replacing traditional methods with advanced construction techniques such as AAC block masonry, automatic plastering systems, mechanized concreting, and productivity-oriented site management practices. Comparative quantitative analysis was performed on major construction activities to evaluate the impact of the proposed interventions. The findings reveal that the implementation of VSM-based lean strategies significantly improved project efficiency. The total project execution duration was reduced from 896 days to 677 days, resulting in a time saving of 24.4%, while the overall project expenditure was reduced from ₹4,77,38,238 to ₹4,47,75,724, achieving a cost saving of 6.2%. Activity-level analysis also demonstrated notable reductions in brickwork and plastering duration, labor dependency, and material wastage. The study concludes that Value Stream Mapping serves as a practical and effective lean construction tool for identifying process inefficiencies, eliminating non-value-added operations, and improving construction productivity. The proposed framework offers a feasible roadmap for contractors and project managers seeking sustainable time-cost optimization in residential construction projects.
KEYWORDS
The present study examined the application of Lean Construction through Value Stream Mapping to reduce the overall time and cost involved in residential building construction. Conventional construction methods often lead to higher labor dependency, material wastage, process delays, and poor workflow coordination, which increase both project duration and expenditure. By preparing the Current State Map and Future State Map, the inefficiencies in the existing construction process were identified and improved methods were proposed. The comparative analysis of brickwork and plastering activities showed significant measurable improvement after introducing advanced construction alternatives. In brickwork, the use of AAC block masonry reduced the cost from ₹61,22,080 to ₹51,54,876 and reduced the execution time from 224 days to 194 days. Similarly, in plastering work, the automatic plastering machine reduced the cost from ₹2,63,875 to ₹2,50,681 and reduced the execution duration from 174 days to 120 days. These results indicate that mechanized and improved construction methods help in minimizing labor effort and increasing productivity. The overall project comparison also confirmed the effectiveness of Lean Construction implementation. The total project duration was reduced from 896 days to 677 days, resulting in a saving of 219 days or 24.4%. Likewise, the total project cost was reduced from ₹4,77,38,238 to ₹4,47,75,724, achieving a direct saving of ₹29,62,514 or 6.2%. Thus, it can be concluded that Value Stream Mapping is an effective tool for identifying non-value-added activities and improving workflow continuity in construction projects. The study proves that by adopting advanced construction methods and proper lean planning, residential projects can be completed in a more economical and time-efficient manner.
[1] Manjunath M., Shivaprasad H. C., Keerthesh Kumar K. S. and Deepa Puthram, “Value Stream Mapping as a Tool for Lean Implementation – A Case Study,” International Journal of Scientific and Research Publications, vol. 4, no. 5, pp. 1–5, 2014. [2] Abhigna E. Desai and Maharshi J. Shelat, “Value Stream Mapping as a Lean Construction Tool – A Case Study,” International Journal of Engineering Research and Applications, vol. 4, no. 8, pp. 39–42, 2014. [3] Vinaya D. More, Dr. Shrikant Charhate and Madhulika Sinha, “Lean Construction Techniques in Indian Construction Industry: Some Analysis,” International Journal of Engineering Research and Applications, vol. 3, no. 4, pp. 54–58, 2013. [4] Barathwaj R., R. V. Singh and Gunarani G., “Lean Construction: Value Stream Mapping for Residential Construction,” Journal of Civil Engineering and Environmental Technology, vol. 2, no. 11, pp. 101–105, 2015. [5] G. Rajkumar, S. Saravanakumar and R. Gowtham, “Applying Value Stream Mapping for Improving Productivity in Construction,” International Journal of Innovative Research in Science, Engineering and Technology, vol. 4, no. 3, pp. 1456–1462, 2015. [6] Nimesha Vilasini and J. R. Gamage, “Implementing Value Stream Mapping Tool in the Construction Industry,” International Journal of Engineering Trends and Technology, vol. 24, no. 7, pp. 352–357, 2015. [7] Murat Gunduz and Ayman Fahmi Naser, “Cost-Based Value Stream Mapping as a Sustainable Construction Tool for Underground Pipeline Construction Project,” Sustainability, vol. 9, no. 12, pp. 2184–2198, 2017. [8] Vinaya D. More, Dr. Shrikant Charhate and Madhulika Sinha, “Lean Construction Techniques in Indian Construction Industry: Some Analysis,” International Journal of Engineering Research and Applications, vol. 3, no. 4, pp. 54–58, 2013. [9] Ankush Naskar and Laukik P. Raut, “Working of Automatic Wall Plastering Machine,” International Journal of Engineering Sciences and Research Technology, vol. 4, no. 5, pp. 611–615, 2015. [10] Rahul Mahajan and Reuben Buthulo, “Quality Control of RMC,” International Journal of Emerging Technology and Advanced Engineering, vol. 3, no. 6, pp. 210–214, 2013.
Publication Date
5/7/2026
Peer Review Type
Double-Blind Peer Review
Review Rounds: 2
Documents
Article Views
2
Total views since publication
PDF Downloads
6
Total downloads since publication
Geographic Reach
5
Digital Preservation: This article is permanently archived on Zenodo and complies with all data preservation standards across major indexing platforms.
Plagiarism Screening
This manuscript has been checked for plagiarism using TurnitinPlagiarismChecker software.
Conflict of Interest
The authors declare no conflict of interest related to this research work.
Funding Information
No funding information available for this research.
Related research in the same subject area
Loading similar articles...