Crossref DOIMemberCiteFactoropen accessissn
SJIF Impact Factor 8.659 | ISSN: 2582-3930
IJSREM Logo

International Journal of Scientific Research in Engineering and Management

(Gateway to Global Scholars - An International, Scholarly, Multi-Disciplinary, Open Access Journal)

Peer-Reviewed Journal Designed to Meet UGC's Quality Parameters

HomeCurrent IssuePast IssuesPay OnlineConferencesEditorial BoardAbout UsContact Us
IJSREM

Loading article...

Follow Us

  • Google Scholar
  • ResearchGate
  • Academia.edu
  • Mendeley
  • LinkedIn
  • Facebook
  • Instagram

Journal Policies

  • Peer Review Policy
  • Publication Ethics
  • Copyright Infringement
  • Refund & Cancellation Policy
  • Terms and Conditions
  • Privacy Policy

Journal Identifiers & Licenses

  • ISSN Verified: 2582-3930ISSN Verified: 2582-3930
  • Crossref DOI: 10.55041Crossref DOI: 10.55041
  • SJIF Ranking: 08.659SJIF Ranking: 08.659
  • Licensed under CC BY 4.0Licensed under CC BY 4.0
  • ISO Certification: 9001:2015ISO Certification: 9001:2015
  • Indexed & Cited In: Google ScholarIndexed & Cited In: Google Scholar

Contact Us

International Journal of Scientific Research in Engineering and Management (IJSREM)

#62/1, New No 7, 1st Cross, 2nd Main, Ganganagar, R T Nagar, Bangalore North, Bangalore, Karnataka, India – 560032
[email protected]+91 93911 67991
logos
logos
Working Hours

Mon – Sat: 9:00 AM – 6:00 PM

Sunday: 10:00 AM – 4:00 PM

+91 93911 67991

© 2026 IJSREM – International Journal of Scientific Research in Engineering and Management. This is an open-access journal. Articles are published under the Creative Commons Attribution (CC BY 4.0) License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

DisclaimerPrivacy PolicyTerms and Conditions
ArticlePeer ReviewedOpen AccessPlagiarism Passed
Paper ID:IJSREM51592

Planning, Scheduling, and Delay Analysis of a Commercial Building Using Microsoft Project (MSP): A Case Study

Stream/Area:

-

Subject:

-

Paper ID:

IJSREM51592

Volume:

9 |

7 |

Jul 2025

Pages:

Publication Frequency:

Monthly (12 issues per year)

DOI
Digital Object Identifier
10.55041/IJSREM51592

License:International Journal of Scientific Research in Engineering and Management follows the Creative Commons Attribution 4.0 (CC BY 4.0) License, allowing free use and distribution with proper attribution.

Share this article:

Authors

SSC

Sakshi Santosh Chougule

PJA

Prof. J. A.Patil

Author Services & Downloads

Full Articles

Abstract

Delay in constructions is one of the common problems in India which usually results in large time overflow and cost increases. This paper examines real-life applicability of planning, scheduling and delay management in commercial buildings projects with the help of Microsoft Project (MSP). Three case studies containing G+4, G+6 and G+7 buildings in Maharashtra, based on elaborate Work Breakdown Structures and base schedules were studied. MSP was used to track progress and Time Impact Analysis (TIA) was used to assess the impacts of delays on project schedules and cost. This analysis showed that the cumulative delay days were 316 and the overall cost incurred due to this delay is ₹1,080,838. among 41 activities. The main delay causes were a shortage of labor, vendor-related problems, and design revision, problems of material procurement, and the environment. Testing comparative results proved that when compared to the manual mode of planning, the dynamic scheduling features of MSP facilitated much better visualization of critical paths as well as loading of resources and modeling of scenarios. The results support the need to incorporate digital tools and proactive delay analysis as key contributors to the efficiency of construction projects, risk management, and decision support within construction projects that are sized in the middle of the spectrum. Key wards – Delay in construction, Work Breakdown Structures, Time Impact Analysis (TIA), Cost Overrun, Commercial Buildings.

KEYWORDS

Cite This Article

Sakshi Santosh Chougule, Prof. J. A.Patil, "Planning, Scheduling, and Delay Analysis of a Commercial Building Using Microsoft Project (MSP): A Case Study," International Journal of Scientific Research in Engineering and Management, vol. 9, no. 7, Jul 2025. https://doi.org/10.55041/IJSREM51592

Full Article/Conclusion

References

Editorial & Review Transparency

Publication Date

7/27/2025

Peer Review Type

Double-Blind Peer Review

Review Rounds: 2

Documents

Review Report (Confidential)
Copyright Form (Office)

Article Metrics & Impact

Article Views

0

Total views since publication

PDF Downloads

7

Total downloads since publication

Geographic Reach

5

Indexing, Archiving & Preservation

Google Scholar
Academia
ResearchGate
Crossref
SSRN
Semantic Scholar
Thomson Reuters
WorldCat
Mendeley
OpenAlex
EBSCO
Zenodo

Digital Preservation: This article is permanently archived on Zenodo and complies with all data preservation standards across major indexing platforms.

Ethics, Compliance & Transparency

Plagiarism Screening

This manuscript has been checked for plagiarism using TurnitinPlagiarismChecker software.

Conflict of Interest

The authors declare no conflict of interest related to this research work.

Funding Information

No funding information available for this research.

Similar & Recommended Articles

Similar Articles by Topic

Related research in the same subject area

Loading similar articles...