Crossref DOIMemberCiteFactoropen accessissn
SJIF Impact Factor 8.659 | ISSN: 2582-3930
IJSREM Logo

International Journal of Scientific Research in Engineering and Management

(Gateway to Global Scholars - An International, Scholarly, Multi-Disciplinary, Open Access Journal)

Peer-Reviewed Journal Designed to Meet UGC's Quality Parameters

HomeCurrent IssuePast IssuesPay OnlineConferencesEditorial BoardAbout UsContact Us
IJSREM

Loading article...

Follow Us

  • Google Scholar
  • ResearchGate
  • Academia.edu
  • Mendeley
  • LinkedIn
  • Facebook
  • Instagram

Journal Policies

  • Peer Review Policy
  • Publication Ethics
  • Copyright Infringement
  • Refund & Cancellation Policy
  • Terms and Conditions
  • Privacy Policy

Journal Identifiers & Licenses

  • ISSN Verified: 2582-3930ISSN Verified: 2582-3930
  • Crossref DOI: 10.55041Crossref DOI: 10.55041
  • SJIF Ranking: 08.659SJIF Ranking: 08.659
  • Licensed under CC BY 4.0Licensed under CC BY 4.0
  • ISO Certification: 9001:2015ISO Certification: 9001:2015
  • Indexed & Cited In: Google ScholarIndexed & Cited In: Google Scholar

Contact Us

International Journal of Scientific Research in Engineering and Management (IJSREM)

#62/1, New No 7, 1st Cross, 2nd Main, Ganganagar, R T Nagar, Bangalore North, Bangalore, Karnataka, India – 560032
[email protected]+91 93911 67991
logos
logos
Working Hours

Mon – Sat: 9:00 AM – 6:00 PM

Sunday: 10:00 AM – 4:00 PM

+91 93911 67991

© 2026 IJSREM – International Journal of Scientific Research in Engineering and Management. This is an open-access journal. Articles are published under the Creative Commons Attribution (CC BY 4.0) License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

DisclaimerPrivacy PolicyTerms and Conditions
ArticlePeer ReviewedOpen AccessPlagiarism Passed
Paper ID:10.55041/IJSREM13943

Scheduling of Multi-Storey Hostel Building using Primavera P6

Stream/Area:

-

Subject:

-

Paper ID:

10.55041/IJSREM13943

Volume:

6 |

5 |

May 2022

Pages:

Publication Frequency:

Monthly (12 issues per year)

DOI
Digital Object Identifier
10.55041/IJSREM13943

License:International Journal of Scientific Research in Engineering and Management follows the Creative Commons Attribution 4.0 (CC BY 4.0) License, allowing free use and distribution with proper attribution.

Share this article:

Authors

SKP

Sri Krishan Pandey

AV

Adarsh Verma

SKM

Saurabh Kumar Maurya

JK

Jitendra Kumar

PK

Puneet Kumar

SPS

Surendra Pratap Singh

Author Services & Downloads

Full Articles

Abstract

Now a day’s construction gets delayed in the site due to the factors such as inefficient management, design issues, economic variation, coordination failure between time schedule and execution etc. Poor scheduling of tasks is one of the main causes. Scheduling in construction project is the process of listing of tasks with a planned start and finish date. The scheduling is very important in construction projects and it cannot be neglected since it plays a crucial role in success of the project. Proper scheduling will ensure the completion of the project on time and within budget. It helps to outline the pace of the work and show how the tasks are executed. It also defines method and sequence in which materials are delivered. Overall, it permits adjustments to accommodate changes and unanticipated events. The big problem faced by the construction sector is not able to manage the fund allocated for the work and not able to complete the work in targeted days. This can be overcome by the implementation of effective scheduling in the construction field. Scheduling is a very important component of successful time management. Primavera is an enterprise project portfolio management software (EPPMS). It includes project management, scheduling, risk analysis, opportunity management, and resource management. This project report deals with scheduling of Boys Hostel building by using Primavera P6 software. Ongoing project is located at Rajkiya Engineering College, Mainpuri and manual scheduling data collected from the site. Project is under U.P. Rajkiya Nirman Nigam. Software uses CPM technique to schedule activities of the project. Cost required for the project execution is ultimately saved with proper scheduling process. For scheduling and creating WBS of the project, required steps are taken. We had created Gantt Chart view of the scheduling, allocated resources to activities and assigned roles to each resource and created calendar of the project based on the holidays in India. In this project by using Primavera P6 software we had properly created WBS, schedule the activities and properly utilized resources and thus reduced the actual duration of the project and ultimately finish the project economically.

KEYWORDS

Scheduling Primavera Optimization Dynamic WBS Execution CPM Resource Management Variation Estimate Economic.

Cite This Article

Sri Krishan Pandey, Adarsh Verma, Saurabh Kumar Maurya, Jitendra Kumar, Puneet Kumar, Surendra Pratap Singh, "Scheduling of Multi-Storey Hostel Building using Primavera P6," International Journal of Scientific Research in Engineering and Management, vol. 6, no. 5, May 2022. https://doi.org/10.55041/IJSREM13943

Full Article/Conclusion

References

Editorial & Review Transparency

Publication Date

5/29/2022

Peer Review Type

Double-Blind Peer Review

Review Rounds: 2

Documents

Review Report (Confidential)
Copyright Form (Office)

Article Metrics & Impact

Article Views

0

Total views since publication

PDF Downloads

3

Total downloads since publication

Geographic Reach

5

Indexing, Archiving & Preservation

Google Scholar
Academia
ResearchGate
Crossref
SSRN
Semantic Scholar
Thomson Reuters
WorldCat
Mendeley
OpenAlex
EBSCO
Zenodo

Digital Preservation: This article is permanently archived on Zenodo and complies with all data preservation standards across major indexing platforms.

Ethics, Compliance & Transparency

Plagiarism Screening

This manuscript has been checked for plagiarism using TurnitinPlagiarismChecker software.

Conflict of Interest

The authors declare no conflict of interest related to this research work.

Funding Information

No funding information available for this research.

Similar & Recommended Articles

Similar Articles by Topic

Related research in the same subject area

Loading similar articles...